Here is the communication from the board president to the building homeowners received today:

As you can probably tell from the e-mails and other updates, there has been plenty of activity here at Brooks Tower in the past few weeks, and things are only going to get busier in the weeks ahead. By early next week our Owners’ representative, the Bergeman Group, will begin evaluating bids from four highly regarded construction firms for the removal and replacement of nearly all plumbing in the building. It’s too early to provide a reliable dollar figure until the Bergeman team makes sure all bids are on the same page regarding scope of the work. But we hope to present the top two bids and dollar amounts to the Board for a vote on June 21st. The Board will then select a contractor based on cost, experience, track record with buildings similar to ours and other factors.